United Kingdom, Poland - Small Modular Nuclear Reactors
Baseline schedule creation spanning project inception to commercial launch
Creating a Nuclear Project Regulatory Track for the UK (ONR) and Overseas (USNRC & EC)
Creating schedules for international bids
Managing, planning and tracking the progress of engineering work packages
Developing a logistics path and assessing factory production indicators
Conducting research on earned value management (EVM) and budgeting
Developing QSRA program capabilities and conducting risk assessments
Configuration of reporting systems and cyclical schedule updates
Presence at workshops, conferences and meetings with the RR SMR team, potential clients and external stakeholders
Poland, Spain, UK - Data Centres
Client-side project planning management.
Configuration of reporting systems, progress monitoring, and reporting using Power BI.
Contractor schedule control and development of scheduling and reporting requirements.
Claims analysis (Time - Impact Analysis).
Milan, Italy - Data Centres
Creating and verifying project schedules
Conducting audits of subcontractors' progress
Collaborating with project management and department heads to adjust planned tasks
Identification and evaluation of critical activities and paths with limited flexibility
Generating project status reports and communicating them to project management and stakeholders
Monitoring schedule execution and productivity levels
Documenting delays and disruptions
Harwell, UK - Synchrotron
Development of a tender program.
Project risk assessment.
Developing a supply chain engagement strategy.
Support of the Construction Department.
Identification of delays and assessment of their impact on contract implementation.
Development of a baseline project schedule for construction and acceptance.
Wrocław, Poland - Electric Car Battery Manufacturing Facility
Developing procedures and protocols to effectively streamline project processes.
Creating planning processes and standards, progress monitoring tools.
Preparation of tender schedules at the pre-construction and construction stages.
Monitoring schedule execution and productivity levels.
Troubleshooting and advising on any project organization issues that arise, providing expert advice on viable solutions.
Harwell, UK - mRNA Vaccine Factory - Laboratories and Active Substance Production
Development of a project schedule spanning from preparatory work to commissioning.
Creation of a reporting system (Power BI) and regular schedule updates.
Identification of delays and assessment of their impact on contract execution.
Preparation of narrative reports for the Project Engineer.
Braine l’Alleud, Belgium - Active Substance Production
Creation of a matrix of system dependencies and automated tools checking the correctness of schedule sequence
Establishing a reporting system and preparing regular schedule updates.
Creation of a Power BI Reporting System to monitor work progress
Ghent, Belgium - Active Substance Production
Creating a baseline project schedule for construction and commissioning
Creation of a reporting system and preparation of periodic schedule updates
Leiden, Netherlands - Active Substance Production
Development of a baseline project schedule for construction and acceptance.
Preparation of acceleration scenarios in terms of the Contractor's contract requirements.
Establishing a reporting system and preparing regular schedule updates.
Created Serri Power BI reports for progress reporting
Warsaw, Poland - Railway Station, Pedestrian Bridge, Railway and Roads
Development of Contractual Schedules for Construction, Engineering, Sanitary, Electrical, Railway, and Earthwork.
Time-Impact analysis and reporting.
Identification of delays and assessment of their impact on contract execution.
Analysis of reported progress and preparation of claim specifications to safeguard the contractor's rights under the FIDIC Contract.
Support for the claims management team.
Preparation of narrative reports for the Project Engineer.
Warsaw - Czachowek, Poland - Railway Stations, Bridges, Railways, Roads, Supporting Infrastructure
Development of Contractual Schedules for Building, Engineering, Sanitary, Electrical, Railway, and Earthwork.
Time-Impact analysis and reporting.
Identification of delays and assessment of their impact on contract execution.
Analysis of reported progress and preparation of claim specifications to safeguard the contractor's rights under the FIDIC Contract.
Planning support for the claims management team.
Preparation of narrative reports for the Project Engineer.